Case Study
Published: 31st July 2015
Rotork supports Natural Resources Wales’ automated flood alleviation scheme

Overview

The flood alleviation scheme on the River Mwldan in Wales was identified as having some issues of unreliability with its electric actuators as a consequence of heavy rainfall. Following this discovery, Rotork IQ12 intelligent electric actuators were installed on site, ensuring that the system ran more reliably.

Challenge

An extended scope contract performed by Rotork Site Services has successfully delivered full automation of a flood alleviation scheme protecting the historic town of Cardigan in West Wales. The project involved replacing unreliable actuators from another manufacturer, installing a PLC control cabinet and interfacing with the existing river level sensor and telemetry system.

Solution

The flood alleviation scheme on the River Mwldan above Cardigan was constructed 20 years ago by the local authority to reduce flooding in the local area. It consists of a V notch weir, an over-spill grid into a culvert that travels approximately half a mile through the hillside into the estuary and three flushing penstocks. In 2006 the scheme was adopted by Natural Resources Wales (NRW – formerly Environment Agency Wales) to operate and maintain. Since then, NRW has installed CCTV and telemetry to enable remote visual monitoring of the site from central control rooms and mobile devices.

During recent periods of intense rainfall the weir has been at the point of over-topping and, to reduce the flood risk, two of the penstocks were opened. As well as proving the vital importance of the penstocks, these events also highlighted the unreliability of the electric actuators originally installed. Poor environmental sealing had enabled moisture to enter electrical enclosures, causing operational failures. The problem was aggravated by the design of the actuators’ manual operating mechanism, which demanded lengthy and laborious handwheel operation to open the heavy penstocks. As a result, NRW decided to replace the actuators and at the same time introduce full automation of the flood alleviation scheme.

Result

The extended scope contract awarded to Rotork encompassed all aspects of the task, enabling Rotork to organise the total supply of the work together with project management services. A major benefit of this approach for the customer is the simplified contractual route that the extended scope contract enables, by minimising the number of separate sub-contractors that need to be employed.

Rotork’s responsibilities included an initial survey, removal of the old actuators and replacement with new, installation of a PLC control cabinet with HMI for local control and indication, interfacing with the level sensor and telemetry system and commissioning of the completed installation. The new Rotork IQ12 intelligent electric actuators installed are controlled by the PLC, using the signal from the river level sensor. The actuators operate in 5% travel increments (each equivalent to approximately 45 mm of penstock travel) at trigger points.

Operation of the site is now fully automated and remotely monitored. The Rotork actuators provide position feedback and alarm signals to the PLC and the telemetry system. Alarms include obstructed penstock, which the actuator will automatically close, and power failure, after which the system will automatically restart. If necessary, the automatic system can be overridden and the actuators can be operated remotely via the telemetry system or locally via the HMI panel on the PLC control cabinet.

Mike Haley is the NRW MEICA electrical engineer who has been responsible for automation upgrade project. He comments: “The scheme using Rotork actuators has successfully introduced the level of automation and remote monitoring that we required and restored reliability to the operation of the three penstocks. Rotork actuators have a proven record of reliability at other NRW sites, including an installation which has been operating in an exposed coastal environment for 30 years.”

Download Case Study

News and Updates